Wastewater Treatment & Drinking Water Upgrades Project
Wastewater Treatment & Drinking Water Upgrades Project
On this Page:
Project Overview
This project involves the installation of new water and wastewater lines that will connect the City of Martensville to the City of Saskatoon’s regional utility infrastructure. The Partnership will provide additional wastewater treatment capacity to support future residential and commercial growth, while delivering a long-term, sustainable, and reliable servicing solution for the community.
Construction activities will be taking place in the following areas:
- 10th Avenue South (Rock Ridge Road), near the City of Martensville’s Organics Waste Site
- The Highway 11 and railway crossing along Township Road 384
- Lutheran Road, extending east toward Highway 11
Work will primarily involve:
- Horizontal directional drilling (HDD) to install new underground water and wastewater pipelines
- Excavation of temporary drill entry and exit pits
- Backfilling and restoration of the roadway following pipeline installation
- Temporary traffic control measures, including signage, barricades, and lane accommodations as required
Project Updates
November 6, 2026
Auger Boring (AB)
– The contractor has ordered a reverse pipe rammer to pull the existing 6m wastewater steel casing and auger head from the entry. This equipment is due to arrive next week.
– The auger bore work is expected to take over 1 month once work begins, due to the existing ground conditions.
Horizontal Directional Drilling (HDD)
– The 240-drill rig is currently setup at the Lutheran Road and RR3053 intersection and is working eastbound along Lutheran Road. The drill has completed a large section with the 42-inch ream. There is a portion of the segment that has not completed the 36-inch ream because the reamer had broken and was sent for repairs. Pipe pullback for this segment is not expected until next week.
– The 100-drill rig is currently setup on the corner of Lutheran Road and RR3053, performing the last drill segment along RR3053. The water main pipe pullback is anticipated by Friday, November 6.
Traffic Control & Notifications
– The Lutheran Road & Highway 11 intersection has been re-opened with heavy vehicle restrictions. Two lanes are present with a temporary lane extension to the north to accommodate eastbound and westbound traffic.
– Additional traffic control will be set up in the following week(s) once the WWM drill is set up at the southwest corner of Lutheran Road & Range Road 3052 at STA 2+857 to drill westbound along Lutheran Rd.
– No additional traffic control will be set up for the 100-drill once drilling begins heading east on Lutheran Road as the existing traffic control is sufficient.
October 21, 2026
Auger Boring (AB)
– Pilot tube auger bore was successfully completed with minimal disruptions. The steel casing has been welded and is ready to be inspected prior to installation. The contractor will monitor AB progress as work continues. 24-hour shifts to start Monday, October 26th.
Horizontal Directional Drilling (HDD)
– The 240-drill rig is currently setup at the Lutheran Road and RR3053 intersection and is working eastbound along Lutheran Road. The drill has completed the 24-inch ream for the first segment, and the wastewater main pipe pullback is anticipated by the end of this month.
– The 100-drill rig is currently setup on the corner of Lutheran Road and RR3053, performing the last drill segment along RR3053. The water main pipe pullback is anticipated by the end of this month.
– Contractor is looking to coordinate HDD segments just west of the CN tracks to allow open-cut excavations to occur under the same traffic control detour period as the AB work. Work tentative for 3-4 weeks from now as the WWB AB is nearing completion.
Open-Cut Excavation Work
– Contractor looks to complete segment tie-ins in the near future. Work anticipated to begin the week of November 2 or 9.
IWI Line Repairs
– Contractor to coordinate with IWI as the 240-drill is nearly completed its drill segment.
Traffic Control & Notifications
– Road Closure Trial Run – Lutheran Road closure is to expire on Friday October 23rd.
– An additional road closure of approximately two weeks is anticipated, with an unknown start date that is dependent on the AB crossing work. Contractor will ensure the road request is made well in advance prior to implementation.
– Cameras have been installed near the drill locations in response to traffic control non-compliance and safety concerns.
September 9, 2026
Work on the IWI line is progressing. Pipe pullback is underway on the water main section located on the east side of Highway 11.
Temporary lane construction is progressing at the workzone near the CN Rail Crossing. Steel plates will be installed prior to the placement of gravel to protect the existing drainline. Once the temporary lane is complete, a new phase of traffic control plans will be implemented.
August 26, 2026
The wastewater line installation is fully set up and operational on the southwest side of the Lutheran Road and Range Road 3053 intersection. The pilot boring was completed over approximately one to two days.
The watermain drill is now set up on the east side of Highway 11, with the pilot hole expected to be completed by the end of the week. Pipe pullback is anticipated to be completed by the end of August. Once complete, the drill will be moved to the starting pad to begin drilling the watermain south along Range Road 3053.
Range Road 3053 traffic control will continue to stay in place for the foreseeable future, with lane closures extending north to accommodate pipe staging.
August 24, 2026
The contractor has started work east of Highway 11 on Range Road 382, with granular base currently being delivered to the work area.
The roadway will remain open while this portion of the work is underway. Please use caution when travelling through the area and watch for construction activity.
August 17, 2026
Work continues on the Joint Water & Wastewater Project, with several key steps moving forward this week.
The contractor is nearly finished fusing the pipe for the first section of the project along 10th Avenue South and Range Road 3053. Pipe pullback is scheduled to begin this week. As additional utility work is completed in this area, the lane restriction is expected to extend further south toward Lutheran Road.
Traffic lane restrictions along 10th Avenue South are anticipated to remain in place until September. Please use caution when travelling through the area and follow all posted traffic controls.
Preparation is also underway for the next section of drilling, located just east of Highway 11. A granular pad was constructed on August 14, and drilling is expected to begin this week.
This drill will run from Highway 11 toward the City of Saskatoon connection point.
10th Avenue South Workzone
As part of this project, a temporary a temporary lane restriction will be in place on 10th Avenue South near the City’s Lagoon and Yard Waste Site access. Reduced speed limits and traffic signage will be in place throughout the work area. Motorists are asked to slow down, follow posted instructions, and use caution while travelling through the area.
Traffic Impacts
- Beginning the week of August 3rd, 2026, traffic on the highlighted section of 10th Avenue South (see Project Map) will be reduced to one lane of alternating traffic for approximately two months.
- Temporary traffic lights will be installed on the north and south sides of the work area to safely manage vehicle movement through the work area.
- Traffic will alternate in each direction, with each signal phase holding traffic for approximately 90 seconds.
- Another traffic light will be located at the Lagoon and Organics/Yard Waste Site access to assist vehicles entering and exiting the site.
10th Avenue Workzone Map
Access to Services Maintained
- Access to the Lagoon, and Yard Waste Site will remain available throughout the project
- Please continue to follow posted signs, traffic controls, and any updated notices
Oversized Loads
- Restrictions will be in place for oversized loads during the lane closure
- If you require access for an oversized load, please contact the City in advance to discuss requirements and make necessary arrangements
Frequently Asked Questions (FAQ)
- Will this phase of the project impact current wastewater services?
- No. Existing wastewater services will continue to operate throughout the project.
- How long will construction take?
- This phase of the project is estimated to take 2 months to complete. The construction schedule is dependent on favourable weather and site conditions, and timelines may be adjusted in the event of delays. Updates will be posted on the City’s website, as well as the City’s social media accounts.
10th Avenue Workzone Map
Lutheran Road Workzone
Following completion of work on 10th Avenue South, crews will continue along Lutheran Road from 10th Avenue going east towards Highway 11. This work is expected to continue for approximately 20 weeks.
Highway 11 and Railway Crossing Workzone
Construction at Highway 11 and the railway crossing along Township Road 384 is anticipated to begin in mid-August, subject to flagging protection and final approvals. This work is expected to take approximately eight weeks to complete.
Project Overview