2020 Road and Repair Projects

The Federal Gas Tax Fund program in Saskatchewan is administered by the provincial government to help support municipalities.

Of the $1.5 million dollars budgeted in Martensville for roadways in 2020, $900,000 of that is funded by the Federal Gas Tax Fund.  This includes: 

-This work consists of milling the existing asphalt, replacing the subgrade structure, and overlaying a new asphalt driving surface.
-There are also some concrete repairs being completed at the same time to improve storm drainage in
the area. 

 -This work consisted of milling the existing asphalt, leveling, and overlaying a new asphalt driving surface.

-This work consisted of milling the existing asphalt, leveling, and overlaying a new asphalt driving surface. The work will be broken up in two sections, the first closure will be from 1st Street South to 4th Street South.
-The second section of the road closure will be from 4th Street South (including the intersection) to 6th Street South.
-A third section added, included extending work south to City limits

-This work consisted of milling the existing asphalt, leveling, and overlaying a new asphalt driving surface. ---Some concrete work adjacent to the roadway was also completed

- Expected to take one day to complete,
-SUTO (Super Ultra Thin Overlay) 

- Expectecd to take 2 days to complete
- SUTO (Super Ultra Thin Overlay) 

-Work to rebuild the road and pave due to sewer main replacement project

Main Street Extension, Joint Project with RM of Corman Park

- Extend paving of Main Street from 16th Avenue North to Range Road 3052