Main Street Paving Project- Phase 1 and 2

Beginning Monday, August 30, 2021, road construction will begin on Main Street. The work will be broken up into two phases to minimize detours. The phases and their schedules are shown below. 

Phase 1 – 5th Ave N to 8th Ave S – Road will be closed from Monday August 30, 2021, to Wednesday September 1, 2021

Phase 2 – 2nd Ave N to 5th Ave N – Road will be closed from Wednesday September 1, 2021, to Friday September 3, 2021. 

Residents can place their garbage bins in their regular place on garbage collection day, and the City’s contractor will ensure the bins are picked up.  

This schedule is weather permitting and may be subject to change. Please watch for updates on the City’s Website and Facebook Page.

If you have any questions or concerns, please contact City Hall at (306) 931-2166.

 