Martensville Overpass project Commences- Project update for April

On March 20th, 2017, Kiewit officially broke ground with clearing and grubbing operations at the Warman and
Martensville job sites.

Construction of the Warman and Martensville Interchanges Project is underway!
On March 20th, 2017, Kiewit officially broke ground with clearing and grubbing operations at the Warman and
Martensville job sites. Kiewit’s focuses for April operations are as follows:

Martensville:
· Topsoil Stripping and Stockpile
· Structural excavation for centre bridge pier foundation
· Piling at bridge structure
· SaskPower utility relocations
· Installation of Martensville Stage 1 Detour signage

Traffic Management:
· Effective April 5th, 2017 – Martensville Stage 1 Detour

o Closure of Range Road 384 between Highway 12 to the Western project limits
Further construction and traffic updates will be made available on the Project website at
www.wminterchanges.ca.