In April, Kiewitwas nearing completion of the piling operations at the Martensville site. Kiewit continued with topsoil stripping and embankment operations at Martensville and Warman.
Kiewit’s focuses for the month of May are as follows (weather permitting):
Martensville:
· Complete pile driving for the bridge foundations
· Embankment for the West and East bridge abutments
· Topsoil stripping and stockpiling
· Grading operations for the Highway mainline
· Structures work on the centre bridge pier and abutment foundations
· Utility relocates
Traffic Managment Martensville
o Range Road 384 closure still in effect
o No additional changes to Martensville traffic
for further information visit www.wminterchanges.ca or open the latest update