• 03 Jul 2017
    Overpass Project Update- July 2017

    In June, Kiewit continued with topsoil stripping and roadway embankment operations at both the Warman and Martensville job sites. Structures work continued on both of the bridge structures. Utility relocates are ongoing. Kiewit’s focuses for the month of July are as follows (weather permitting):
     

    Martensville:

    · Topsoil stripping for the highway mainline

    · Road line embankment and grading

    · Culvert install along the highway mainline

    · Structures work on the bridge centre pier column and wing walls

    · Utility relocates

    Full monthly project update.

    Visit www.wminterchanges.ca for information about the project and see images from the project cameras.

     